Huntersville Elementary Modular Classrooms Complete on Gilead Road
Modular classrooms at Huntersville Elementary, 200 Gilead Road, are complete, providing swing space during the $66 million replacement school project.

Modular classroom work at Huntersville Elementary School, 200 Gilead Road, is complete, providing swing space during construction of the 45-classroom replacement school. ADW Architects is the architect; Swinerton Builders is construction manager and general contractor.
Five new modular classrooms were added next to the lower parking lot in summer 2026. Five older modular units were taken out of use and will be removed, with foundations and walkways demolished in phase one of the replacement project.
Building permits carry values of $47,166,000, $6,820,000, $5,500,000, and $2,824,000. Swinerton's bid packages included plumbing, rebid with a June 9, 2026 bid date.
The work falls under the $2.5 billion CMS 2023 bond referendum. The replacement school is estimated at slightly over $66 million and opens for the 2028-2029 academic year.
- Address
- 200 Gilead Road, Huntersville, NC 28078
Every filing, company, change and story we have on this project, completed as of our latest read of the record.
Every new Charlotte project, in your inbox at 8.
Read from the permits and filings each morning and written up as news. Free.
Free · unsubscribe anytime · no spam, just projects
Groundbreak covers 8 markets
Popular this week in Charlotte
- 1
Digital Realty's CLT13 Data Center Under Construction in West Charlotte
- 2
Ares' 341-Unit Plaza Midwood Project Under Construction
- 3
Alliance Residential Closes on Enderly Park Site for 336 Units
- 4
Cadia Village Matthews Breaks Ground at 14300 Idlewild Rd
- 5
Caldwell Commerce Center Building 2 Under Construction in Charlotte
More from Charlotte
All coverage ↗
Amazon-Leased AXIAL Rapid Commerce Sells to Pacolet Milliken

Michaels Buys Mint Hill Site for Active-Adult Apartments

Steele Creek Recycling Center Under Construction on John Price Road

Marie G. Davis Middle School Renovation Underway in Dilworth

Firehouse 47 ARFF Station Under Construction at CLT