Hicks Field DFW11 Data Center Under Construction in North Fort Worth
Construction is underway on Hicks Field DFW11, a 251,303 SF data center at 10200 Hicks Field Rd, the first of five buildings on ACS Group's 107-acre campus.

Construction is underway on Hicks Field DFW11, a two-story, 251,303 SF data center at 10200 Hicks Field Rd in far north Fort Worth. It is the first of five buildings planned on ACS Group's 107-acre Hicks Field campus. Corgan Associates designed the project; the owner is ACS DC Hicks Field Road, LLC.
Crews started January 26, 2026, after TDLR registration on December 16, 2025. Building permits total roughly $368 million, including one valued at $327 million. Estimated construction cost is $280 million, with completion expected June 26, 2027.
The building includes two 25,075 SF data halls and 14,993 SF of administrative space. Oncor Electric will serve the facility through an adjacent private substation. Full campus capital investment is about $2.1 billion across two phases, with construction planned through 2034.
The Fort Worth City Council approved a 10-year economic development program agreement on April 8, 2025.
- Address
- 10200 Hicks Field Rd, Fort Worth, TX 76179
- Floors
- 2
- Sq ft
- 251,303
- Completion
- Jun 26, 2027
Every filing, company, change and story we have on this project, under construction as of our latest read of the record.
Every new Dallas-Fort Worth project, in your inbox at 8.
Read from the permits and filings each morning and written up as news. Free.
Free · unsubscribe anytime · no spam, just projects
Groundbreak covers 8 markets
Popular this week in Dallas-Fort Worth
More from Dallas-Fort Worth
All coverage ↗
QTS FTW1 DC1 Expansion Under Construction in Fort Worth

Loews' 507-Room Americana Hotel Under Construction in Arlington

JPS Medical Outpatient Building Under Construction in Fort Worth

Perot Museum Plans Four-Acre Expansion in Dallas

Allen Corporate Center Lands $13.1M Acquisition Loan