Walnut Creek Wastewater Treatment Plant expansion underway at 7113 FM 969, Austin, enhancing local infrastructure.

The Walnut Creek Wastewater Treatment Plant expansion at 7113 FM 969, Austin, is under construction. Led by Austin Water with AECOM architecture, the project aims to modernize facilities, enhancing wastewater management. Completion is set for December 31, 2032.

Strategically located in the Walnut Creek neighborhood, this expansion supports Austin's infrastructure growth needs.

The project file
Walnut Creek Wastewater Treatment Plant Expansion and ModernizationUnder Construction
- Address
- 7113 FM 969, Austin, TX 78724
- Completion
- 2031
Every filing, company, change and story we have on this project, under construction as of our latest read of the record.
The Austin Brief Β· free
Every new Austin project, in your inbox at 8.
Read from the permits and filings each morning and written up as news. Free.
Free Β· unsubscribe anytime Β· no spam, just projects
Groundbreak covers 8 markets
Popular this week in Austin
- 1
Nearly 900 Acres Leave Uhland ETJ for 700 MW Data Center Campus
- 2
300-Unit, 30-Story Tower Proposed for Rio Grande Street
- 3
234-Unit Senior Living Project Filed in Leander's Northline
- 4
TML Proposes $60M Municipal Center in Downtown Georgetown
- 5
Austin Council Fast-Tracks Data Center Rules, Eyes Hyperscale Ban
More from Austin
All coverage β
Samsung Sets November Groundbreaking for Taylor Fab 2

DML Capital Buys Northwest Austin Office Building

Tri Pointe Acquires 85.6 Acres for 410 Homes at Pearson Ranch

Austin Housing Fund Approves $21M for 261 Units in 5 Projects

St. John South Under Construction in Northeast Austin