DataBank Builds 425K SF DFW13 Data Center in Red Oak

DataBank is building DFW13, a two-story, 425,170 sq ft data center on Stainback Rd in Red Oak, designed by JHET Architects and targeting 2027 completion.

Site plan of DataBank's Red Oak campus showing DFW13 as a future phase along Stainback Road
Site plan of DataBank's Red Oak campus showing DFW13 as a future phase along Stainback RoadImage via DataBank

DataBank's DFW13, a two-story, 425,170 sq ft data center, is under construction on Stainback Rd in Red Oak. Owner of record is DB Data Center Red Oak, LLC; JHET Architects, PLLC is the design firm.

Rendering of a data center building at DataBank's Red Oak campus in Red Oak, Texas
Rendering of a data center building at DataBank's Red Oak campus in Red Oak, TexasImage via DataBank

Construction began March 1, 2026, following TDLR registration on January 5, 2026. The $325 million project is privately funded, with completion targeted for December 31, 2027.

Aerial rendering of a data hall and generator yard at DataBank's Red Oak campus
Aerial rendering of a data hall and generator yard at DataBank's Red Oak campusImage via DataBank

The building pairs data center space with an office component. It is planned for roughly 60 MW of critical IT load and will support air-cooled and direct-to-chip liquid cooling.

DFW13 is part of DataBank's 292-acre Red Oak campus, planned for up to eight two-story data centers totaling 1.6 million-plus sq ft and 480 MW. Phase 1 includes a 400 MW on-site substation tied to the ERCOT grid. DataBank previously secured $2.0 billion in construction financing for the campus's first three buildings: DFW9, DFW10, and DFW11.

The project file
Databank Red Oak - DFW13Under Construction
Open the file ↗
Address
Stainback Rd, Red Oak, TX 75154
Floors
2
Sq ft
425,170
Completion
2027

Every filing, company, change and story we have on this project, under construction as of our latest read of the record.

The Dallas-Fort Worth Brief · free

Every new Dallas-Fort Worth project, in your inbox at 8.

Read from the permits and filings each morning and written up as news. Free.

Free · unsubscribe anytime · no spam, just projects

Groundbreak covers 9 markets

  1. 1

    Hughes House III Under Construction at 4912 E. Rosedale St.

  2. 2

    Klyde Warren Park Westward Expansion Breaks Ground in Dallas

  3. 3

    Carrier Plans $600M Manufacturing Center at AllianceTexas

  4. 4

    3.9M SF Data Center Campus Approved in Midlothian

  5. 5

    Springs District Office Tower 39% Pre-Leased, Groundbreaking Nears

More from Dallas-Fort Worth

All coverage ↗