Nashville Data Center Rules in Force; Permit Moratorium Runs to Dec. 1
Metro's countywide data center zoning rules cap facilities at 500,000 square feet, with a permit moratorium in effect through Dec. 1, 2026.

Metro Council's countywide data center regulations passed on third reading July 21, with a moratorium on new permits running through Dec. 1, 2026. The zoning bill, BL2026-1391, and companion building materials measure BL2026-1392 passed unanimously. Councilmember Rollin Horton (District 20) was the lead sponsor.

The law bans data centers over 500,000 square feet countywide. Large facilities require a special exception from the Metro Board of Zoning Appeals, with a public hearing. Council members strengthened the requirements before passage, including by increasing distance buffers.

Mayor Freddie O'Connell backed the moratorium with Executive Order 59 on June 15, directing Metro departments to study data center impacts, and supported the ordinance.

His $544.7 million Capital Spending Plan, his fourth, was filed with the Metro Council, which begins consideration of it at its Oct. 5 meeting.

The rules land as DC Blox pursues a 69,200-square-foot, 10-megawatt facility at 648 Grassmere Park near the Nashville Zoo, with a second building over 200,000 square feet proposed. Metro is considering using eminent domain to acquire the Grassmere Park property.
Every new Nashville project, in your inbox at 8.
Read from the permits and filings each morning and written up as news. Free.
Free · unsubscribe anytime · no spam, just projects
Groundbreak covers 9 markets
Popular this week in Nashville
More from Nashville
All coverage ↗
State Approves Developer Selection for Capitol Parking Lot Redevelopment

Bank OZK Plans First Nashville-Area Office at 5 City Blvd

Marston Music Row Opens at 1740 Division St

Oracle Breaks Ground on $4.5B River North Campus

75-Unit Condo Building Proposed for Germantown Site