Tampa Approves South Howard Flood Relief and Streetscape Project

Tampa has approved a combined flood relief and streetscape rebuild of the South Howard Avenue corridor through SoHo, with completion targeted for August 2030.

City of Tampa flood modeling shows reduced flooding (right) after the South Howard Flood Relief Project improvements
City of Tampa flood modeling shows reduced flooding (right) after the South Howard Flood Relief Project improvementsPhoto credit City of Tampa

The City of Tampa has approved the South Howard Flood Relief and Streetscape Project, a combined drainage and streetscape rebuild along the South Howard Avenue corridor in SoHo. Completion is targeted for August 31, 2030.

The project addresses chronic stormwater flooding along the corridor, which runs through SoHo and Hyde Park. Pairing flood relief with surface streetscape work lets the city rebuild drainage and the public realm in a single construction program.

Streetscape improvements include 10-foot sidewalks, traffic calming, upgraded pedestrian crossings, and enhanced lighting. Landscaping, permeable pavers, and green infrastructure will absorb stormwater at street level, supplementing the larger drainage system.

The approval moves the project into the city's active capital program. The Sept. 17 vote, 4-3, approved Kimmins Contracting's $92.7 million guaranteed maximum price, within a $100.4 million total. Utility relocation is expected to begin in November, with major drainage work starting next spring. The 2030 target reflects the multi-year timeline typical of combined drainage and streetscape rebuilds, where underground utility work precedes surface construction.

South Howard is a primary north-south route through South Tampa, linking the SoHo entertainment district with Hyde Park Village to the north and residential neighborhoods to the south. The improvements target vehicle, pedestrian, and bicycle traffic.

Correction, Oct. 21, 2026: An earlier version of this story said engineering and design come next. The Sept. 17 vote approved Kimmins Contracting's $92.7 million construction price, and utility work is expected to begin in November.

Address
South Howard Avenue corridor, Tampa, FL
Completion
Sep 2030

Every filing, company, change and story we have on this project, approved as of our latest read of the record.

The Tampa Bay Brief · free

Every new Tampa Bay project, in your inbox at 8.

Read from the permits and filings each morning and written up as news. Free.

Free · unsubscribe anytime · no spam, just projects

Groundbreak covers 9 markets

  1. 1

    The Linden Breaks Ground on 170-Unit Workforce Housing in Brandon

  2. 2

    Permits issued for $70M Fieldhouse on Fowler at MOSI

  3. 3

    Coral Walk Student Housing Breaks Ground Near University of Tampa

  4. 4

    Ferguson Office Rises at Gasworx, Fully Leased Ahead of Delivery

  5. 5

    301 Exchange Breaks Ground at US-301 and Sligh in Tampa

More from Tampa Bay

All coverage ↗