Manatee County Approves 12-Month Data Center Moratorium
Manatee County commissioners unanimously approved a 12-month moratorium on data center and large-load customer applications in unincorporated areas.

The Manatee County Board of County Commissioners unanimously approved Ordinance 26-42, a 12-month moratorium on data center and large-load customer applications in unincorporated areas. The vote came at the board's October 8, 2026 meeting.

The moratorium pauses acceptance, processing, and approval of building permits, site plans, development orders, development agreements, special permit uses, rezonings, and comprehensive plan amendments for data centers and other large-load customers or facilities with substantial electrical, water, wastewater or other utility demands.

The measure follows Florida Senate Bill 484, which took effect July 1, 2026 and established local government authority to set strict standards and deny data center projects. During the 12-month moratorium, staff will recommend code updates covering use definitions, compatibility considerations, water and electricity consumption, noise abatement, environmental impacts, design standards, appropriate zoning districts, future land use categories, process requirements and fees.
County planner Jay Stearman presented the item. Commissioners involved include Jason Bearden, Amanda Ballard, Bob McCann, and Chair Tal Siddique.
Every new Tampa Bay project, in your inbox at 8.
Read from the permits and filings each morning and written up as news. Free.
Free · unsubscribe anytime · no spam, just projects
Groundbreak covers 9 markets
Popular this week in Tampa Bay
- 1
Ryan Companies Wins Approval for 475K SF Temple Terrace Project
- 2
Permits issued for $70M Fieldhouse on Fowler at MOSI
- 3
The Linden Breaks Ground on 170-Unit Workforce Housing in Brandon
- 4
Ferguson Office Rises at Gasworx, Fully Leased Ahead of Delivery
- 5
Sembler Breaks Ground on Publix-Anchored Willowbrook Center
More from Tampa Bay
All coverage ↗
Hillwood Proposes 500K SF Auburndale Data Center on Pace Road

GLOVIS Secures 32 Acres for Port Tampa Bay Auto Terminal

Tampa Council Kills 325-Unit South Tampa Waterfront Project

Starke, Faropoint Break Ground on North Tampa Industrial Park

Roche Bobois Tower Set to Start Construction in St. Pete