Travis Heights Reclaimed Water Main Project (Direct Reuse Strategy Project)
Travis Heights area, Austin, Texas
approved
Basic Information
- Project Type
- infrastructure
- Building Use
- public space
Size & Capacity
Square Footage
Timeline
- Construction Start
- 1/1/2026
- Expected Completion
- 6/1/2028
- Completion Year
- 2028
- First Discovered
- 2/6/2026
Financial
- Total Construction Cost
- $6,038,565
Internal Notes
The project will add approximately 4,500 linear feet of 24-inch Ductile Iron and HDPE reclaimed water main to Austin Water's reclaimed water system, enhancing the reliability of service for reclaimed water customers in the Travis Heights neighborhood.