Automated Transit Network Demonstration Pilot (Glydways ATN Pilot)
College Park, near Hartsfield-Jackson Atlanta International Airport, Georgia International Convention Center to Gateway Center Arena
under construction
Basic Information
- Project Type
- mixed use
- Building Use
- mixed use
Size & Capacity
Square Footage
Timeline
- Construction Start
- 2/18/2026
- Expected Completion
- 12/31/2026
- First Discovered
- 2/6/2026
- Last Covered
- 4/8/2026
- Articles Published
- 2
Financial
- Total Construction Cost
- $18,000,000
- Financing Amount
- $3,000,000
Internal Notes
The project involves the installation of EV charging stations at Hartsfield-Jackson Atlanta International Airport, enhancing the airport's infrastructure for electric vehicles.
Developers
Owners
General Contractors
Related Articles
- Hartsfield-Jackson Approves Aviation Encumbrance Program
4/8/2026
Hartsfield-Jackson Airport approves a mixed-use development program.